Budget for Student Latrines

Student Latrines (Completed in July of 2009)

Boys' Latrines

Boys' Latrines

Girls' Latrines

Girls' Latrines

Making Bricks

Item Unit Quanity Cost per unit Total
Cement Bags 50 15,500 TZSH 775,000TZSH
Bricks (labor) Bags 50 2,000 TZSH 100,000 TZSH
Sand Lorry trips 7 70,000 TZSH 490,000 TZSH
Subtotal 1,365,000 TZSH

Latrine Building

Item Unit Quantity Cost per unit Total
Sand Lorry trips 2 70,000 TZSH 140,000 TZSH
Cement Bags 50 12,500 TZSH 210,000 TZSH
Iron Rods 12 meters 14 15,000 TZSH 210,000 TZSH
PVC 5 12,000 TZSH 60,000 TZSH
Binding Wire 5 kgs 1 20,000 TZSH 20,000 TZSH
Paint Can 6 10,000 TZSH 60,000 TZSH
Pebbles Lorry trip 1 250,000 TZSH 250,000 TZSH
Iron Sheets 20 10,000 TZSH 200,000 TZSH
Subtotal 1,715,000 TZSH

Roofing

Item Unit Quantity Cost per unit Total
Boards Pieces (2X6) 30 4,500 TZSH 135,000 TZSH
Boards Pieces (1X8) 20 7,000 TZSH 140,000 TZSH
Soft Wood 1X10 8 5,000 TZSH 5,000 TZSH
Nails 1 kg 6 3,000 TZSH 18,000 TZSH
Locks 8 3,000 TZSH 24,000 TZSH
Subtotal 357,000 TZSH

Toilets

Item Unit Quantity Cost per unit Total
Sink 8 15,000 TZSH 120,000 TZSH
Buckets 4 5,000 TZSH 20,000 TZSH
Wash Basin 4 10,000 TZSH 40,000 TZSH
Subtotal 180,000 TZSH
Subtotal 3,617,000 TZSH
Labor 800,000 TZSH
Transport 400,000 TZSH
Total 4,817,000 TZSH ($4,000.00)