Budget for Teachers Latrines

Teachers’ Latrines (This project was completed in November of 2009)

tidbits as the final days wrap up 009

Item Measurement Quantity Cost per Unit Total
Cement Bags 18 TZSH 15,500.00 279,000.00 TZSH
Making Bricks Labor 350,000.00 TZSH
Subtotal 629,000.00 TZSH
Roofing
Iron sheets 4 12,000.00 TZHS 48,000.00 TZSH
Boards 1 X 10 10 9,000.00 TZHS 90,000.00 TZSH
Nails Kg 4.5 3,000.00 TZHS 13,500.00 TZSH
Paint 2 12,000.00 TZHS 24,000.00 TZSH
Iron rods 10 15,000.00 TZSH 150,000.00 TZSH
Elbow pipes 4 5,000.00 TZSH 20,000.00 TZSH
PVC 2 15,000.00 TZSH 30,000.00 TZSH
Sealant 1 5,000.00 TZSH 5,000.00 TZSH
T Pipes 2 4,000.00 TZSH 8,000.00 TZSH
Subtotal 388,500.00 TZSH
Other
Doors 5 7,000.00 TZSH 35,000.00 TZSH
Locks 2 3,500.00 TZSH 7,000.00 TZSH
Sinks 2 15,000.00 TZSH 30,000.00 TZSH
Subtotal 72,000.00 TZSH
Labor
Digging pits 60,000.00 TZSH
All additional 350,000.00 TZSH
Subtotal 410,000.00 TZSH
Transport
Sand Lorry 3 70,000.00 TZSH 210,000.00 TZSH
Pebbles Lorry 1 250,000.00 TZSH 250,000.00 TZSH
Subtotal 460,000.00 TZSH
TOTAL 1,959,500.00 TZSH

$1,473.31 Dollars